Inspections

Which Projects Require Inspection?

Construction or work for which a permit is required is subject to inspection by the Building Code Department (BCD). 

Requesting an Inspection

Twin Cities Campus

The person doing the work authorized by a permit must notify the Building Code Department that the work is ready for inspection. For inspections, please contact the inspector designated on your permit. 

The permit holder and/or person doing the work calls the inspector for an inspection request. Provide the permit number and provide the inspector with clear directions including building name, room number(s) and floor where work is being performed, and items to be addressed in the inspection. 

System Campuses

Inspection requests and scheduling for all permit types for system campus locations (i.e., Crookston, Duluth, Morris) must be made using the online application system

Review your permit status and inspection requirements with your project field staff to determine any required inspection needs you have for the upcoming week. Once you have determined your inspection needs, please use the BCD website to access the online application system to submit your request(s) for required rough-in inspections before work is covered or final inspections before permits are closed.  BCD staff will review these requests and contact you to verify scheduled times. 

Contacting Your Inspector

You will find inspector contact information on our Our Team page.

Inspection Site Access Requirements

The construction or work must remain accessible and exposed for inspection purposes until approved. The person requesting the inspection required by the code must provide access to, and means for, inspection of the work. It is the responsibility of the permit applicant to ensure the work remains accessible and exposed for inspection purposes. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the BCD. Any portion of work that does not comply shall be corrected and that portion of work must not be covered or concealed until authorized by the BCD.